Construction update Monday 2 May to Friday 6 May 2011

03 May 2011

Central Plant Building – Western Side.

Central plant services are now operating. This metal cladding to the services tower is 75% complete and when this is completed we can remove the scaffolding and then complete the civil work below this area. We are programmed to have all this work completed by the end of May 2011.

Boyle Building – Eastern Side.

The Building envelope is virtually complete and the services fit-out are well underway throughout the Building. Work will commence around the Boyle Crescent side of the building with the re-establishment of ground levels up against the new building. Total completion of the Boyle Building is planned for the end of September 2011.

Redevlopment of the internal areas within the existing University Buildings.

Work is continuing in six different areas within the existing Buildings as part of an ongoing redevelopment process and this will continue for years to come with the site containers / site offices in Park Avenue being part of this process. Four areas in two buildings have recently been completed and Building 503 Basement and Building 502 Level 2 are presently going through a demolition phase.