Construction update Saturday 26 March to Friday 1 April 2011

28 March 2011

Central Plant Building – Western Side

Central plant services commissioning is ongoing.

The southern services tower plywood cladding is complete. This services tower will be finished in metal cladding and this will commence over the next few weeks. The civil site works to the western side of Building 504 is 80% complete. All the current work in this area should be complete by the end of April 2011..

Boyle Building – Eastern Side

The Building envelope is virtually complete and the services fit-out are well underway throughout the Building. Work will commence around the Boyle Crescent side of the building with the re-establishment of ground levels up against the new building. Completion of the Boyle Building is planned for the end of September 2011.

Redevelopment of the internal areas within the existing University Buildings

Work is continuing in six different areas within the existing Buildings as part of an ongoing redevelopment process and this will continue for years to come with the site containers / site offices in Park Avenue being part of this process. We will have four areas in two different buildings nearing completion and other areas presently going through a demolition phase.